Jump to content

Recommended Posts

Posted

Good to know! I'm not sure if it has that adjustment but I'll open it up and see if there are any less accessible controls. As far as I know, I can only adjust output current and a handful of program operation controls for ram and hold time. Wouldn't that be neat if I didn't have to fire up the kiln!

Not all those who wander are lost. -J.R.R. Tolkien

-Shards of the Dark Age- my blog
-Nine Worlds Workshop-

  • 2 weeks later...
Posted

Lots of uninteresting but steady work going on. I'm almost entirely through the 'small' parts getting everything de-rusted and primed with a rust converting primer. The last piece that isn't the frame is one of the helve cushion bell housings that's sitting in evaporust until tomorrow.

primer.jpg

 

Here's what the primer looks like over the cleaned metal. It does a good job at protecting the surface now that it has been through some combination of evaporust, the needle descaler, and a wire wheel. Everything that isn't a bearing surface will be getting the same treatment with exception of the nuts and bolts which I have decided to wire wheel, degrease, and cold blue. For the bearing surfaces it'll be just a little sanding and/or scotchbrite, then oiled in service.

 

wire bottle brush.jpg

 

For the threaded holes, I've chased everything with a drill brush of whatever size is closest but big enough to bite, then followed with a tap to clean up the threads and cut out any rust intrusion. This has worked very well, and so far I've gone through every threaded hole in the frame and assembly (excluding nuts) and used a 3/8-16, 1/2-13 (thankfully no 1/2-12 debacles like on my flypress), 3/4, 7/8, and 1". For most of these I needed bottoming taps due to the captured nature of the holes. For almost all of them there has been a surprising amount of cutting action. Whether from rust, old gunk, or the original taps being a slightly undersized version compared to the 130 year newer version, I have no idea.

 

bore hone.jpg

 

For the bearing holes I ran a bore hone through them after the wire brush to get any of the little burs and surface rust out. They do not behave well if there is a keyway cut into that same bore...

 

bolt.jpg

 

In the machining realm I identified the last smaller bolt that needed to be remade, so I took about half the remaining piece of the hex stock I forged and cut a new bolt and matching nut. There is still one more, slightly larger bolt I need to forge so I may either upset the stock for that or cut a new piece altogether.

 

axle nut.jpg

 

While at the lathe, I remade the large nut for the helve axle pivot. This one is much larger and fits better. Depending on the forthcoming heat treatment of the axle I may end up remaking it too with a forged hex rather than machined so it's larger. Then I can also do the finish turning post hardening.

 

axle nut 2.jpg

 

There's something satisfying about the forged/machined combination that I really want to do more of.

 

treadle axle.jpg

 

Last up for now is the pivot for the treadle linkage. There was a great deal of rust on the section that sat inside the frame which made it difficult to remove. Instead of remaking it I turned down about 1/16" off the section that sits inside the hollow of the casting so it won't bind again. The rear pivot was missing so I need to remake that one to replace the small threaded rod that was in its place, and I'll do the same thing to that one. The ends are full original size so they fit correctly in the frame bore. My original plan, which I was actually rather excited for, was to use the old spot drilled holes in the end and remount it between centers. I even dug out the old lathe dog I got from the Klockar's shop up in San Francisco when I was helping rescue some machinery up there a few years ago. But alas the faceplate on the lathe was just big enough that the dog woldn't reach the drive slots so I put it back in the 3jaw.

 

Next up on the docket is to remake the stainless parts, mostly the plates that pretension the yoke cushions, the other rubber damper cone tensioners, and the shafts that apply stability/tension to the yoke. I should also have the top half of the frame off tomorrow to continue the soul crushing job of getting all the old crust off, then primed and painted. For the bottom half I think I am going to try turning it over so I can really clean and protect the inside of the frame. Given that the bottom is open to the air and how corroded the shafts through that section were, it needs something in there to keep it protected.

  • Like 3

Not all those who wander are lost. -J.R.R. Tolkien

-Shards of the Dark Age- my blog
-Nine Worlds Workshop-

Posted

Lots going on the last few days with most of it still lost in progress as I wait on a few workholding solutions to get me through the final stainless steel machining. However I managed to get the upper frame half off today and the final cleaning done. With a coat of primer on it I must say it is really coming together! Seeing such a large piece ready for paint is a spectacular feeling. Tomorrow hopefully I'll be able to get the lower frame finished, but getting it flipped over to access the underside is a daunting task. Just getting the upper half off was, if the picture of the rig is any indication, a harrowing experience! But with luck the lower frame can stay closer to the ground and mitigate most of the risk of catastrophe. frame jib.jpg

 

I had a section of tube frame lying around that I added another triangle to the top so it could receive a section of I beam. With a matching 2T rolling gantry and chain hoist, it was just able to lift high enough to pick up the frame half. On the other end I had the trusty engine hoist which has now officially done more than any engine hoist should ever have to do. I did check to see if it would lift the weight before slewing it off the concrete pad but all the same the sag under load was alarming because it was already at max height and barely level without load.

 

frame upper.jpg

 

frame upper2.jpg

 

Even as just a coat of primer it looks great. I may go back with the bottle brush and clean out the threaded holes again before final assembly but otherwise it's ready for a proper coat of paint! The stuff is an oil based farm duty paint and with the weather cooling down it will probably take a week to dry if not longer. In a perfect world I'll paint everything at once, so when the lower frame is clean and primed it's on to the good part!

  • Like 2

Not all those who wander are lost. -J.R.R. Tolkien

-Shards of the Dark Age- my blog
-Nine Worlds Workshop-

Posted

Looking great. it will be super satisfying to put parts back together again.

 

I just love how beautiful the cast shapes are, sculptural form for a machine part.

  • Like 1

There are no secrets, one just has to ask the right questions.

 

 

Posted

For real! Getting into the bottom of the frame the casting is a gorgeous shape all around. The way the structure and draft angles come together in deliberate ways is really neat. I'm trying to figure out how to do some gold embellishments on it somewhere and I was suggested some pinstriping in places which might be really nice if I can put it in a tasteful design.

  • Like 2

Not all those who wander are lost. -J.R.R. Tolkien

-Shards of the Dark Age- my blog
-Nine Worlds Workshop-

Posted

What a monumental project. You are making incredible progress on a beautiful piece of history restoration. 

  • Like 1

“So I'm lightin' out for the territory, ahead of the scared and the weak and the mean spirited, because Aunt Sally is fixin’ to adopt me and civilize me, and I can't stand it. I've been there before.”

The only bad experience is the one from which you learn nothing.  

 

Josh

http://www.dosgatosdesignsllc.com/#!

https://www.youtube.com/channel/UCdJMFMqnbLYqv965xd64vYg

J.States Bladesmith | Facebook

https://www.facebook.com/dos.gatos.71

https://www.etsy.com/shop/JStatesBladesmith

Posted

Thanks! It'll be a wonderful feeling to get this beauty back into service! From what I have been able to learn about it, it's been at the very least 15-20 years sitting unused but probably far more than that. I'm about to commit to the castable urethane for the cushions so once the paint dries there's nothing stopping me from full assembly. I knew it would be a handful to get things up and going again but somehow even still, things take longer than expected!

  • Like 1

Not all those who wander are lost. -J.R.R. Tolkien

-Shards of the Dark Age- my blog
-Nine Worlds Workshop-

Posted

Another couple of good machining days wrapped up today with the semi-final bit of stainless work. The last few bits involved tig welding a few things together and some final machining, and now that it's done I'm rather pleased with how it turned out.

 

cushion dampener.jpg

 

The first replacement parts out of stainless are the helve cushion dampers that put tension on the back end of the helve iron. These bits take pressure from a screw, one top and one bottom, which compress a stack of rubber disks. Whether or not they are original I have no idea (probably replacements) but they are in good shape so I can reuse them. Everything in contact with the rubber was fairly rusty, so to save someone the trouble in the future I'm making it all stainless. This reference piece is in good condition overall but the other was about 20% of the original material for how badly it corroded. So instead of making just the one I decided to just do both at the same time. The top is an easy taper with a hole drilled half way through the thickness, the other side with a recess that accepts one of the rubber disks to keep it from sliding out of alignment.

 

stainless billet.jpg

 

I managed to find this stainless drop at the local metal supplier, a monstrous thing to put through the saw in spite of how small it looks in the vice. Unfortunately it is smaller than I need, but the good news is that it's the exact diameter of the rubber so I needed to find a way to make a collar around the circumference that will do the holding.

 

dampener angle.jpg

 

Using the good part as a reference, I matched the existing taper with the compound slide on the lathe and locked the angle. No math involved!

 

dampener blank roughing.jpg

 

A quick facing on both sides to clean up the saw chatter and it's time to turn the cone. I left the diameter of the flat bit that will have the hole in it so I know where to turn down to. Again, the less measuring on old rusty stuff the better.

 

dampener blank.jpg

 

Due to the switching around of the vice jaws I had to run the lathe backwards and cut from the far side of centre. Nothing monumental but another weird tooling setup to avoid crashing the chuck into the slide.

 

cushion dampener blankj.jpg

 

After a spot drill and boring out to the final size/depth, the pair is ready for wrapping. This is one of the few times I have worked with stainless to this degree and I was surprised by how well it behaved. I forget if it's 303 or 304 which is notoriously difficult to machine but this was the other one. Nice easy chips coming off and no work hardening to be found.

 

slip roll.jpg

 

It happened that a 3' length of flat bar was the perfect length to get the two collars out of. A trip to the slip roller and gradually bringing them around got them close. Due to the size of the roller mandrels I could not bring them the full distance around so the rest was up to clamps.

 

cushion dampener fixturejpg.jpg

 

As many clamps fit around the workpiece is usually the exact number needed for it to sit right. Because this piece will not really be doing anything other than sitting under compression, I could probably have just added a few tabs and been fine so there being a slight bit of flat at the end of the rolled collar that would not clamp out will do nothing untoward.

 

cushion dampener weld.jpg

 

I rarely tig weld and have never done much on material this thick, but it was a surprising treat. Not the most consistent welds around but for structural integrity it's significantly more than it needs.

 

cushion dampener2.jpg

 

Here is the old and crusty bit vs new. I'd say that's a significant improvement! I neglected to get a picture of it but the underside of the collar ring leaves about a half inch of space to hold onto the rubber disk.

 

tension bar.jpg

 

Next up are the mystery rods that pass through the vertical yoke supports. These are the ones I had to cut in order to get the helve/yoke/eccentric linkage removed from the frame. Again, the rust where in contact with the rubber made it all but immoveable. Instead of turning them out of a single piece, I decided to join a bar of the correct diameter with a machined lower receiver. I still do not fully understand what this piece is for but I am fairly confident that at the least it allows a pretension to be put on the rubber cylinders so the thing can be put together, then the bars unthreaded to relax it into the final space it has to fill. Second to that, they will also keep the cylinders aligned inside the frame so any load does not cause them to deflect and/or jump out of alignment.

 

bar shank flats.jpg

 

The lager shoulder receiver turned down to a very slightly smaller diameter than the originals so it could fit into the frame without need of a hammer, then drilled in a way that I ended up thoroughly regretting. For about an inch of what is top in the above picture, I threaded with 3/4-10 threads which accept corresponding threads on the bars. The remaining 3" or so is reamed to 3/4" for reasons that made sense at the time. Because I do not have the final length of the bars yet, I left them long to be trimmed down once I can start putting things back together and get a measurement from. Because of that I needed the shoulder receiver to be very coaxial to the bar so when it goes back in the lathe for threading it does not turn into a helicopter.

 

tension bar tap.jpg

 

However, I learned very quickly that threading with a tap, even aligned with the tailstock in the lathe to start off the cutting on centre, the depth of cut is not perfectly consistent around the circumference of the hole. I would have single point cut them but the boring bar is 3/4" which means it doesn't fit when cutting in a 3/4" hole...

 

tension bar end.jpg

 

So when I cut threads on the bar and chased them with a die, the tolerance of the reamed hole was too tight to allow the very slightly eccentric threads to engage the shoulder receiver. In the end I turned a small taper into the bar threads and again very slightly back from where the threads ended to allow for a minute amount of wobble as the bar threaded into the receiver. At the end of the hole the full diameter of the bar matches with the reamed hole so there is still a good amount of accuracy in the setup. We shall see how well that all worked out when time comes to finish the threads on the other end.

 

tension bar welded.jpg

 

By the time everything was tightened down as far as humanly possible, there was just enough to weld a nice fillet around. The idea behind this setup is that the end with the flats on it can be held with a wrench while the nuts on the other end are tightened/loosened to adjust the spring tension. But because the bar can theoretically drop down out of the machine there needs to be a set of jam nuts on the top end, so this larger bit needs to essentially be one piece.

 

tension bar weld.jpg

 

I was a little nervous how this would go turning down the weld with a button cutter. Welds can be incredibly hard but it ended up mostly fine with a little bit of chatter.

 

turned ends.jpg

 

I didn't go all the way down to clean metal because it's an aesthetic job anyway but it felt wrong leaving the ugly grinding where I had to remove the paint from the threaded bar before welding.

 

tension bars.jpg

 

And here are the two bars with the original. That one seems to be at least partially forged which is neat. If machining long thing sections was easier I might have tried it, but it's hard to beat getting the right size off the shelf.

 

Tomorrow I think I'm going to put the first coat of paint on as many parts as possible and continue pondering how to overturn the lower frame section so I can get in there and clean it out. In the parts department, the final metal bits are the two stainless plates that will be the bottom compression surface for the above bars, pressed by the shoulders of the larger cylinders. I have one set of nuts to make, and a final bolt that I may try forge welding a new head onto. The shank and threads are in perfect shape and worst case I remake it anyway. Onward!

  • Like 3

Not all those who wander are lost. -J.R.R. Tolkien

-Shards of the Dark Age- my blog
-Nine Worlds Workshop-

Posted

Managed to get the first coat of paint on the bulk of the parts today and said and done it took about 4 hours crawling around with a little light in the other hand to make sure I didn't miss anywhere. Everything that isn't a bearing surface got painted, including the inside of the eccentric wheel that slides incrementally around the drive shaft. What little spillage into the bearing faces will be sanded later anyway to polish the surface and the holes will get another lick of the hone. The roughness of the casting texture and corrosion in some places made it difficult to get in and seal the surface fully but it was back and forth until all was well. I may go back and put a second coat on but we'll have to see how much paint is left. I have two cans and about 75% of the first one covered everything save the lower frame. For the underside of the lower frame I have some leftover industrial primer and paint from a different job so I'll use that. It is not the low gloss so I didn't want to use it for any of this but underneath in a place that won't be seen again for another hundred years is no sweat. I'm going to let this dry for several days and reassess how ambitions I am about a second coat. Fortunately, because everything is held together with bolts, everything has a convenient place to hang from so it isn't any half coverings and flipping. The larger bits were tricky to get into position and I was a little worried about the sawhorses supporting some 500lbs but no casualties! It feels great to have these all essentially ready to go now. For final assembly I may have to run a tap through the smaller holes that partially filled with paint but anything above 3/8 will sort itself out.

 

painted frame upper.jpg

 

painted small parts.jpg

 

painted helve pieces.jpg

 

painted shaft couplings.jpg

 

 

  • Like 2

Not all those who wander are lost. -J.R.R. Tolkien

-Shards of the Dark Age- my blog
-Nine Worlds Workshop-

Posted

Today I worked through a handful of odd tasks namely because I hardened the rear helve axle today and it's always a time intensive process if fairly hands off.  I did try the induction forge to get a hard jacket on an otherwise softer interior but the power wasn't there for the size of stock. So it was into the kiln and the waiting commenced.

 

hardening.jpg


This vertical air bath kiln has treated me very well in the handful of years I've had it, but it takes quite a while to get up to heat. I think somewhere around an hour and a half, maybe a little faster. With the steel sitting upright on its head in the centre of the chamber, I let it soak for 20min and quenched in McMaster 11s oil. It was the only medium I had that was sufficient volume to handle to size and seemed to work without issue.

 

axle heat treatment.jpg

 

To keep the surface as clean as possible I gave it a healthy covering of anti-scale which mostly blasted off in the quench. A few bits still clung to the surface but underneath the steel is in very good condition.

 

axle temper.jpg

 

As soon as the kiln cooled enough I tossed it back in to begin the tempering. I ended up letting it soak for 2hr at 750, staying in as the kiln cooled down for another couple of hours. I may let it run again tomorrow but I want to examine it first and measure any changes in straightness or size.

 

rear shafts.jpg

 

While that was cooking, I was able to excavate a piece of round bar to turn down a matching shaft for the lower frame where the treadle is mounted. The one with the middle painted is the original, and the second one is to replace what had been a bit of 1/2" threaded rod. I don't know exactly what it is for but I suppose it's something to do with the linkage to the idle wheel or shaft clutch release. The frame has two sets of holes for these and given the fairly robust size it seemed strange that so small a piece was in there.

 

rear lower shaft end.jpg

 

Because the half inch bar was so loose, there is a great deal of corrosion on those mating holes which will need some clever solution in the near future. So, assuming that they are the same as the one with the original shaft, I made this one to match and checked it against those holes.

 

rear lower shaft.jpg

 

Similar to the other one, I reduced the middle length slightly to take paint and keep any future rusting from making it so difficult to remove.

 

eccentric bolt head.jpg

 

Last for the day was this bolt that holds the eccentric linkage to the drive shaft. The other one is in fine condition, and other than the head this one was too. Whatever happened to it, about half of the hex is virtually gone. Interestingly the bolt head seems to have been originally forge welded on so I gave it a go to fixing it the same way.

 

eccentric bolt collar.jpg

 

Grinding off most of the damaged section to get a clean welding surface, I wrapped a bit of flat bar around 3/6 of the hexagonal sides. Fortunately I have a small swage block with a side of hexes that matched well enough. Taking as many welding heats as I could until it seemed solid, the bit appears to have taken.

 

eccentric bolt weld.jpg

 

Dropping the shank down a 3/4" hole and truing up the head a little, the bolt is starting to look passable. Because the stock I used was a little wide, the head came out lopsided and after forging a bit more I took it to the lathe and faced both sides so it would sit flat in the machine.

 

eccentric bolt pair.jpg

 

And here is the repair next to the other original. Not bad! There's a little pitting left from some of the rust damage but it gives it character. A bit of filing on the sides to bring the proportions back and it's ready to go back into service.

 

Next up on the docket is getting the lower frame cleaned and primed/painted, casting the upright helve cushions, and finding some wood for the helve beam. Most daunting and probably the most involved is going to be finding a solution to the missing drive wheel. It's an irregular (large) size and I cannot find anything even remotely close to use which means I'll have to fabricate something. Learning more about lineshafts and flatbelt driven machinery,  many of the wheels that size had rims rolled out of plate (fairly easy) and joined with spokes to a cast iron hub (less easy). If I can find a lone hub or a large enough wheel to take one from I can probably make it work with a new rim. About a year ago I did some work on a project that is strikingly similar to this where I had to make an axle driving spoked wheel to turn a very, very large log. Although precision was not as important for that application, it was surprisingly difficult to make the thing balanced, concentric, coaxial, and coplanar.

 

  • Like 4

Not all those who wander are lost. -J.R.R. Tolkien

-Shards of the Dark Age- my blog
-Nine Worlds Workshop-

Posted

Thanks! Getting really close to reassembly now and I can hardly contain the excitement! Unfortunately most of what is left is slow going so it'll be an exercise in patience for me. Especially because most of the final pieces of the puzzle require sequential solutions which draws it out even more!

Not all those who wander are lost. -J.R.R. Tolkien

-Shards of the Dark Age- my blog
-Nine Worlds Workshop-

Posted

As I get the lower frame sorted out I’ve had a fair amount of time to think over a few things and have a couple of questions if anyone happens to have insight-

 

With the hammer in the smallest (3000lb!!) pieces it can be in I’m reconfiguring a baseplate/lifting/moving foundation and want to put some sort of matting under a steel plate to both help with impact dampening and level to the very not level concrete. Plywood would be easier but I’m outside for now and historically it rains enough in the winter that I don’t want anything absorbent touching the steel. So the classic option is a rubber horse stall mat from Tractor Supply. There’s a great deal of discussion on these and their merits (cost effectiveness) over other things like industrial conveyer belting or the more purpose made vibration control mats. Has anyone used the stall mat on older mechanical hammers? It seems a lot of the negative feedback is on much lighter frames like 25-50lb little giants. After lifting up the lower frame yesterday the entire section under the sow block is solid and therefore outrageously heavy. The matting comes in 3/4” thickness which seems like it will be fine with the 5800 lb of combined hammer weigh plus another few hundred for the plate. 
 

Which leads me to the less easy question. The rubber mats are 65 durometer, precisely what I need for the helve yoke cushions. My initial plan was to case them out of urethane as a single piece, and I even have the molds ready to go. However I need around 3+ gallons which unsurprisingly is not cheap. If I can cut a bunch of disks and stack them together, would there be any issues with that? A single mat would be enough for all 4 cushions and about 1/5 the price of the castable urethane. Even the offcut from the base might be enough although likely just slightly short (of course it would be). I just started looking into vulcanizing rubber cements although the tie rods through the cylinders would probably be enough to keep it together once it’s under load. I’d love to hear any thoughts on it and any potential reasons why it wouldn’t work! 

Not all those who wander are lost. -J.R.R. Tolkien

-Shards of the Dark Age- my blog
-Nine Worlds Workshop-

Posted

I used some of the matting with my previous hammer, which was a lot smaller I guess 2000 pounds and it worked fine, it really cut down on the noise.

One very important thing to consider is working height, for me these old hammers are often way to low to use comfortably. My current hammer sits on almost 8 inches of wooden raft to make it comfortable.

 

If you are buying the matting anyway I would get some extra to use for the helve cushions, I don't think having stacked pieces will make that much difference in running the hammer.

There are no secrets, one just has to ask the right questions.

 

 

Posted

The Jenkins & Lingle Saga.........this is epic.

 

“So I'm lightin' out for the territory, ahead of the scared and the weak and the mean spirited, because Aunt Sally is fixin’ to adopt me and civilize me, and I can't stand it. I've been there before.”

The only bad experience is the one from which you learn nothing.  

 

Josh

http://www.dosgatosdesignsllc.com/#!

https://www.youtube.com/channel/UCdJMFMqnbLYqv965xd64vYg

J.States Bladesmith | Facebook

https://www.facebook.com/dos.gatos.71

https://www.etsy.com/shop/JStatesBladesmith

Posted

Fantastic, thanks for the feedback! I'll double check the height but it didn't seem noticeably low at the time. Then again it was on a pallet and additional beams when it arrived so that's probably about the same extra lifting. I managed to get it up on to blocks and in cleaning the underside a bit today the casting is not particularly flat. So if it comes to it I may put another layer of the matting between the steel plate and hammer frame to have it register nicely. The extra 3/4" wouldn't be an issue then too. With the plate footprint I think I would be very slightly short on material if the plate stays a full 6' for the 5' frame. One other concern I have on a mounting situation now that rain is becoming a temporary concern is that under the back of the frame casting most of the volume is hollow. The rusting inside is not terrible but definitely a factor as I design the base. It would seem undesirable to have a chance to trap water in there and if I use a bit of matting on the back it would act like a gasket. I might try to drill a hole through everything for drainage if that would even work once weight is on it. Or just not worry about it. I unearthed a few extra threaded holes for whatever purpose and are perfectly positioned to funnel water into the casting body. In whatever case, I'm going to plug them with a bolt or something. I think I'm just rambling at this point in a haze of delirium from laying on the ground under the back end of the frame all day needle gunning 130 year old gunk.

  • Like 1

Not all those who wander are lost. -J.R.R. Tolkien

-Shards of the Dark Age- my blog
-Nine Worlds Workshop-

Posted
9 hours ago, John Page said:

I might try to drill a hole through everything for drainage if that would even work once weight is on it.

I think this would be sufficient.  Or cut a slice if that's easier. & add some scrap steel around the hole for weight to make the drain the low point and I'd think you'd be good.

 

One should keep in mind,
we are all both the blacksmith
and iron in the fire...

 

as always

peace and love

billyO

 

 

Posted

In a perfect world I will have the base totally cleaned up early next week. The hollow section at the back was the primary reason I wanted to get primer and paint under there and when I looked inside for the first time I'm really glad I did. It took the better part of half a day to get the frame section off of the pallet and up onto blocks. The beams it was bolted to had been nailed down to the pallet and everything was so old that I had to cut the connections away to free it. Not easy when there's still 3000lbs on top of it! But when I got it up, I hung the back section off of the slight step down in the concrete so I had an extra bit of work space to manoeuvre under. Lying underneath this with the needle descaler and wire wheel for hours on end, getting showered in debris and a century of dirt, shells, rust, grease, and untold other horrors, I finally got everything back down to bare metal. About half way through I changed the angle of my work light and saw that I was merely through the grease but not even close to the casting. Despair! Since there has been more moisture in the air lately and occasional overnight misting I wanted to get this section fully sealed and ready for paint. This red primer is the stuff they use in industrial construction when frames and whatnot are exposed while buildings go up, very tough stuff. What bit I had is nearing the end of its shelf life so I stirred and filtered out the clumpy bits. Drying for a day, it looks perfect. The last bit of cleaning is the remainder of the flat underside, hopefully an easier job. It will have to be in sections however, getting the places not blocked by the timber. If I could safely suspend it on the sow block end I would balance it on the hollow side but it is so monstrously heavy I don't want it in any sort of even remotely imbalanced position while I work under it.

 

base lower.jpg

 

base primer.jpg

  • Like 1

Not all those who wander are lost. -J.R.R. Tolkien

-Shards of the Dark Age- my blog
-Nine Worlds Workshop-

Posted

Nice!  I'm not sure I would have been dedicated enough to clean out the underside of that base.  Good on you!

-Brian

Posted

Bit of a quick update and some very unfortunate news. The shop I work out of is closing down permanently and I have about two weeks before everything is cleared out. I figured this was going to happen but from everything I have been able to find it seemed like it would be well into next year. In that time I was planning on moving and hopefully getting, for the first time, my own place to set up shop in. Now that the timeline is accelerated beyond reason things are very complicated here and with the actual work I have to finish before losing access to equipment this is going, I really regret to say, on the back burner. I was really hoping to have it up and running before moving and with how close it is now it's all the more frustrating. Trying to figure out what to do with about 40,000lbs of machinery is very problematic. What litlte plan I was able to devise has already fallen apart but I have a few last ditch ideas what will hopefully at the very least allow me to park a shipping container somewhere for the next ~6 months.

 

On the power hammer note, I have about a hundred photos still to get through to where it currently sits, but the short of it is getting the frame fully primed and painted, a new key made for the bottom die (hopefully able to reuse the old one to replace the destroyed top die key), a baseplate fabricated, and a few other odd parts made. Things are rather chaotic here for the time being but I'll get those sorted through and posted over the next few days. If it wasn't for the drive wheel being missing in action there might have been a shot at running it before packing it into a container but that optimism is rapidly fading. More to come, hopefully better news.

  • Sad 3

Not all those who wander are lost. -J.R.R. Tolkien

-Shards of the Dark Age- my blog
-Nine Worlds Workshop-

Posted

Bummer John.  Unfortunately I've been there and it's not a fun ride, but hopefully it'll work out for you at least as well as it did for me in the end.  Best of luck!

One should keep in mind,
we are all both the blacksmith
and iron in the fire...

 

as always

peace and love

billyO

 

 

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
×
×
  • Create New...